Euthenics was hired to evaluate the benefits and costs of rehabilitation versus replacement of 2,000’ of 8” sanitary sewer based on CCTV.
Project overview
Scope & delivery
Euthenics was hired to evaluate the benefits and costs of rehabilitation versus replacement of 2,000’ of 8” sanitary sewer based on CCTV. After determining that rehabilitation was the preferred alternative, the firm prepared rehabilitation plans using cured-in-place lining. Other work elements included spot replacement of 100’ of broken VCP pipe, replacement of 37 Orangeburg pipe sanitary laterals with PVC pipe and clean out. All manholes were improved by cementitious coating of interior walls.