Representative project
WATERMAIN REPLACEMENT DESIGN
Euthenics prepared detailed design plans for curb replacement and resurfacing of Glenbury Avenue, Mars Avenue, and Marlowe Avenue.
Project overview
Scope & delivery
Euthenics prepared detailed design plans for curb replacement and resurfacing of Glenbury Avenue, Mars Avenue, and Marlowe Avenue. The work included design of more than 3,600 feet of 8-inch ductile iron cement-lined waterline to replace the existing 6-inch watermain, 12 hydrants, and lead service connections to approximately 266 households. The project also included rehabilitation of 3,575 feet of existing sanitary sewer with CIPP; replacement of 26 catch basins and broken curb; ADA-compliant ramp design; decorative colored stamped brick crosswalks; resurfacing; maintenance-of-traffic plans; stormwater pollution prevention; and landscaping plans.
Contact
Discuss a similar project.
Contact Euthenics to discuss relevant experience, scope, and technical requirements.